WIP limits & Little's Law
Most AI and strategy consultants make the same mistake: they can't do the math. Here's the proof:
Too many projects are started at the same time and worked on in parallel. That costs you real money.
Little's Law makes it clear: if your team is working on 10 projects simultaneously (WIP = 10) and completes on average 2 projects per week (throughput), the average lead time per project is 5 weeks (Lead Time = WIP / Throughput = 10/2).
Reduce the WIP limit to 5, and lead time halves to 2.5 weeks — at the same throughput.
Assuming €10,000 in project costs per week, that saves you €25,000 per project (5 weeks vs. 2.5 weeks × €10,000).
Without WIP limits, unfinished work piles up: with 10 projects of 5 weeks each, you tie up €50,000 per week in incomplete tasks — money that generates no return!
And with the breakneck pace at which technology is improving, you might end up killing one of these projects anyway! That makes WIP limits even more critical.
At the portfolio level, these limits are necessary to avoid six-figure waste and to increase efficiency.
This is why you need Lean principles at multiple levels: team, portfolio and strategy.